A planning application is being prepared for submission to The Highland Council, platforming construction operations on the site of the former Longman Landfill Site, Stadium Road, Inverness.
The following works are envisaged:
- Formation of access road from existing Waste Transfer Station road.
- Outfall to Moray Firth
- Connection to Scottish Water Foul Sewer in Stadium Road
- Badger relocation
- Site strip and vegetation clearance and topsoil clearance
- Service relocation
- Preparation of site via high energy impact compaction
- Vibration monitoring and possible vibration alleviation trench
- Gas alleviation trenches, if required.
- Importation of 99,090m3 (+/- 10,000m3) of material to 450mm below finished ground level.
- Installation of drainage, including foul pumping
- Settlement monitoring during and following contract
The scheme is at an early stage, and we would therefore welcome the input of the local community to help shape the proposals as they evolve.
Below are links to the drawings and documents produced to date, in relation to this project.
We would be grateful if you could use the feedback form below to provide comments on these initial proposals.
Community Consultation events will be held on:
- Wednesday 11th December 2024, 14:00-16:00 (GMT); and
- Wednesday 15th January 2025, 14:00-16:00 (GMT).
At the Caledonian Thistle Stadium, 1st Floor Highlander Suite, Stadium Road Inverness IV1 1FF.
These events will include a display of proposed drawings and an opportunity to ask questions
If you would like further information, please contact us at:
Greg Duncan, NORR, 5 Longman Road, Inverness, IV1 1RY.
Tel: 07785 743624
Email – greg.duncan@norr.com